A complete remodeling of a small bathroom (8’x8′) will take 23 business days on average (4 1/2 weeks in total, including weekends). However, the time will vary depending on the contractor’s expertise and availability, the project’s complexity, customization, available materials, and other factors.
Extensive customization, plumbing, and electrical wiring can take longer time. If you plan to do it yourself, it may take much longer due to your inefficiency (assuming you are not a plumber).
How Long To Remodel a Small Bathroom? Breakdown The Timeline
Task |
Allotted Time (Days) | Notes |
Demolition |
1-2 |
Demolition is the removal of the old one. It should take at most 1-2 days, depending on the materials you are removing. |
Rough Carpentry |
1-2 |
Needed to repair and modify. Might not be needed if the structure is in good shape. |
Plumbing Rough-In |
1-2 |
This includes removing old pipes, replacing floors, and changing toilets, showers, etc. |
Electrical Rough-In |
1 |
Require zero days if you don’t install anything new. |
First Inspection |
1 |
Includes inspecting the conditions, local laws and regulations, building codes, and others. One day is good enough. |
Insulation |
0.5 |
To improve energy efficiency and moisture control. Requires delicate inspection. |
Hang Drywall |
1 |
Includes hanging drywall sheets after insulation is done. One day is enough. |
Finish Drywall |
2 |
After hanging the drywall, joint compound, sanding, and priming are needed. Should be done within two days. |
Paint |
1 |
Easy and simple task. But it requires drying for a day. |
Final Inspection |
1 |
Does not need much time. |
Tile Work |
2 |
It is time-consuming work but optional. |
Cabinetry and Trim |
1 |
Work like mounting bathroom cabinets, countertops, and decorative trim, and others. |
Flooring |
2 |
Installation of new vinyl, tile, or engineered wood flooring. Takes some time but not more than 2 days. |
Hookups, Fixtures, Etc. |
1-2 |
Installation of toilets, sinks, faucets, and other bathroom accessories. Should be done in one day. But two days are required for more accessories. |
Framing |
1-2 |
Framing is required to add doors or windows. 1-2 days are good enough. |
Ventilation System |
1-2 |
Improve air quality and control moisture. Require precision. |
Miscellaneous |
0.5 |
Need for anything left. |
Total | 23 |
how long to remodel a small bathroom – Factors You Need To Know
Are you doing it or hiring a contractor?
Your decision to do it yourself or hire a contractor will impact the remodeling timeline. DIY projects take longer because you lack expertise, resources, and a proper workforce. Conversely, a professional has the expertise, resources, and workforce to do the job quickly.
Current bathroom conditions
The current bathroom condition also impacts the remodeling time. Removing the old fixtures, flooring, and walls will take time. Also, remodeling the old and backdated bathroom with newer accessories will take longer since more features must be installed.
Approval time
You may need approval from local authorities, homeowners’ associations, or building management, which can delay the remodeling process.
Size and Complexity of the Bathroom
Bathrooms with larger sizes and intricate designs will take longer to demolish, install, and finish. For intricate layouts, you need more time to upgrade or relocate plumbing fixtures and electrical systems.
Design Choices and Materials Selection
The design, layout, fixture placement, and material also impact the timeline. Choices should be made beforehand to avoid disruption. Poor or intricate designs and hard-to-find materials will delay the process.
Contractor Availability and Scheduling
Is your contractor ready to work? Is he doing remodeling in other houses simultaneously? If so, it will be tough to get his schedule, which will prolong the timeline.
Agency or sub-contractor
Are you hiring an agency or sub-contractor? An agency generally has a full in-house plumbing, electrical, or carpentry work team. However, a sub-contractor will have to coordinate and communicate with other contractors, increasing the timeline.
Availability of the materials
The availability of materials is important in determining the timeline. A delay in material procurement will delay the working process. It can be for supply chain disruption, custom fabrication, or other reasons.
Custom features
Custom features such as built-in cabinetry, unique fixtures, or intricate tile designs will make the job more complex for the contractor and require more time to complete.
How To Speed Up The Remodeling Process
- Plan before starting the remodeling project. Define the project designs, layouts, and material selection beforehand to avoid disruption during remodeling.
- Work with the contractors that can get your permit quickly from local authorities.
- Try hiring a contractor with an in-house team for plumbing, electrical, and carpentry work. This will provide better coordination and faster work.
- Ensure timely delivery of materials. Collect all the materials before starting the project.
- Use pre-assembled accessories like cabinetry, countertops, or showers to speed up the work.
- Try not to change the plan in the middle of the project.
- Work with the contractor in person. Be available during the remodelling process for suggestions, help, and questions.
Common Remodeling Features For Small Bathrooms
- Installing new fixtures
- Painting the walls and ceilings
- Installing new floorings
- Ventilation improvement
- Adding Open Shelving
- Classic Cabinetry and Storage Solutions
Frequently Ask Questions For how long to remodel a small bathroom
What is the average cost of renovating a small bathroom?
A small bathroom (8’ * 8’) will cost around $6000 to $17000, depending on materials, labor costs, designs, current bathroom conditions, and other factors.
Is it possible to use my bathroom during the remodel?
Yes, you can use the bathroom for emergency purposes only. However, you cannot perform normal tasks such as showering or bathing since keeping the bathroom dry is important during remodeling.
How can I minimize disruption to my daily routine during the remodel?
To minimize the disruption to your daily life, set a clear plan, communicate with the contractor, and set up a temporary bathroom.
Key takeaway
- It generally takes 23 business days to remodel a (8’x8′) bathroom.
- The timeline depends on designs, bathroom conditions, quality of the contractors, and material availability.
- Try to speed up the work with proper planning, supply, and assistance.
- Use simple and minimal materials and accessories to reduce the budget.
- Work closely with the contractor and pay them on time for better performance.
Ready to transform your space? Elevate your home with our expert bathroom remodeling services. Contact us with T and J remodeling to for your bathroom renovation and know more details.
Read T and J All In Remodeling recent blogs
How long to remodel a small bathroom
How long does a full bathroom remodel take
Does a bathroom remodel require a permit
When is a permit required for bathroom remodel